Part 7 · Reading Comprehension
- To:
- Mireille Haddad; Felipe Kaur
- From:
- Sergio Kuznetsov
- Date:
- February 24
- Subject:
- Revised schedule for the Silverlake Crossing photo book
Dear team,
I learned this morning that the paper for our photo book, Silverlake Crossing: Fifty Years in Pictures, will reach the printer on March 7, not February 28. I know this is disappointing after the proofs were approved on February 20. [1] The printer can now start our job on March 10 and needs six working days to print and bind it. [2] The finished books must be at the Silverlake Crossing Community Hall by March 20 for the launch event on March 21.
Mireille, please revise the production schedule, mark every task that depends on the printing date, and send it to me by Wednesday. Felipe, please call the paper supplier tomorrow and ask for a written delivery guarantee. The cover stock has already been delivered and will not change. If the paper has still not arrived by March 8, we will print the inside pages on a lighter stock that the printer already has in its warehouse. [3]
I will meet the printer's account manager on Friday and update you afterward. [4] Please keep this schedule change within the team until then. The authors will be told once the new dates are final.
Thank you for your quick work on this.
Sergio Kuznetsov
Director of Production
Umbdale Publishing
What is the main purpose of the e-mail?
What is Felipe Kaur asked to do?
What is suggested about Mr. Kuznetsov?
In which of the positions marked [1], [2], [3], and [4] does the following sentence best belong? "This option would keep the March 10 start date, although the pages would feel slightly thinner."