- Revised schedule for the Aria 5 air purifier
Dear team,
I am writing to let you know that the certification lab in Merrow Falls has moved our Aria 5 safety inspection from April 22 to April 8. [1] The lab had a cancellation, and I accepted the earlier slot because it lets us reach stores before the spring sales season. [2] I know the timeline is tight, but I am confident we can meet it.
Malia Kaur, please send me the noise and airflow test results by March 21 instead of March 28. You should also ship twelve production samples to the lab by April 1. [3] Leila Mbeki, the packaging design and the instruction booklet are now due on March 25. The booklet text is unchanged; only the diagrams need updating. [4]
The project budget is fixed and overtime will not be approved, so please tell me by Friday if you expect any delay. We will meet on Friday at 9:30 A.M. in Room 4 to review the plan. Thank you for your flexibility.
Esther Haddad
Director of Product Development
Glensera Devices
Why did Ms. Haddad write the e-mail?
What is Ms. Mbeki asked to complete by March 25?
What is implied about the Aria 5 project team?
In which of the positions marked [1], [2], [3], and [4] does the following sentence best belong? "The lab will not begin its inspection without these units."